==Operation==
==Operation==
All [[[[Routes|train routes]] and overlap routes via the level crossing must be [[Revoke Train Route Button|revoked]] before operating the HAT !
All [[Routes|train routes]] and overlap routes via the level crossing must be [[Revoke Train Route Button|revoked]] before operating the HAT !


Durch Drücken der HAT zusammen mit einer Gleistaste wird die Freimeldung, sofern sie für dieses Gleis besteht, zurückgenommen und der BÜ schaltet sich aus. Ist der BÜ für mehrere Gleise freigemeldet, muss die Freimeldung für jedes Gleis einzeln aufgelöst werden, erst dann schaltet der BÜ sich aus.
Pressing the HAT together with a Track Button will revoke the securing, as far as existing for the track, and deactivates the level crossing.
In case the level crossing has been secured for more than one tracks, the securing must be revoked for each individual track first. After that the levelcrossing will be deactivated..


Die Bedienung der HAT ist dokumentationspflichtig, daher ist ein Zählwerk vorhanden.
There is a counter next to this group button as operating the HAT is subject to documentation.


==Examples and Note==
==Examples and Note==

Revision as of 12:30, 28 December 2011

Contents | FAQ | Manual | General Tips and Tricks | Change Log | Multiplayer Manual | Line Operations Manual | Voice Communications | Change Log | Developers pages


Page is under construction. Information is subject to change.

Purpose

Normally a level crossing is deactivated automatically as soon as a train has passed it. The Level Crossing Auxiliary Button (HAT) is used to manually deactivate a level crossing..

Level Crossing Auxiliary Button

Operation

All train routes and overlap routes via the level crossing must be revoked before operating the HAT !

Pressing the HAT together with a Track Button will revoke the securing, as far as existing for the track, and deactivates the level crossing. In case the level crossing has been secured for more than one tracks, the securing must be revoked for each individual track first. After that the levelcrossing will be deactivated..

There is a counter next to this group button as operating the HAT is subject to documentation.

Examples and Note

Zwei Szenarien machen die Nutzung der HAT erforderlich:

  • Die Freigabe des BÜ wird nicht wie vorgesehen hinter dem Zug aufgelöst.
  • Die Zugfahrt findet nicht statt. Dies kann der Fall sein, wenn
    • eine falsche Fahrstraße eingestellt wurde,
    • der BÜ fälschlicherweise gleisbezogen mit der Level Crossing Manually Close Button eingeschaltet wurde oder
    • der Zug nicht abfahren kann, zum Beispiel wegen einer Störung.

Es muss sichergestellt sein, dass kein Zug den BÜ befährt, bevor die HAT benutzt wird! In den meisten Fällen ist dies durch die zwingende Auflösung der Fahrstraßen gegeben, aber man sollte darauf achten, dass wirklich alle Züge rechtzeitig zum Halten kommen.